<p>The construction deviations of super-long span bridges in high-speed railways during the construction phase directly affect the track smoothness after bridge completion, thereby impacting the operational quality of high-speed trains. This study analyzes the main influencing factors of smoothness control in super-long span bridge construction based on their technical characteristics, proposes a construction-phase bridge smoothness control strategy combining segmental assembly control with holistic assessment and adjustment, and investigates smoothness control methods during segmental assembly using the virtual chord measurement method, supported by case studies. The research demonstrates that implementing smoothness control during construction is essential to ensure post-completion track smoothness of super-long span bridges. The proposed strategy effectively translates smoothness control objectives into key construction phases. The virtual chord measurement method proves highly operable and effective for segmental assembly smoothness control. Post-completion multidimensional evaluations using chord measurement and other techniques can guide track smoothness adjustments. Conducting construction-phase smoothness control for super-long span bridges lays the foundation for achieving high track smoothness objectives on high-speed railway bridges.</p>

错误:搜索内容不能为空,请输入英文关键词
错误:关键词超出字数限制,请精简
高级检索

Control method for smoothnessin segmental assembly construction of super-long span bridges for high-speed railways

  • Can Huang,
  • Chengming Peng,
  • Zhaofu Yan,
  • Yuan Zhang,
  • Yifan Deng

摘要

The construction deviations of super-long span bridges in high-speed railways during the construction phase directly affect the track smoothness after bridge completion, thereby impacting the operational quality of high-speed trains. This study analyzes the main influencing factors of smoothness control in super-long span bridge construction based on their technical characteristics, proposes a construction-phase bridge smoothness control strategy combining segmental assembly control with holistic assessment and adjustment, and investigates smoothness control methods during segmental assembly using the virtual chord measurement method, supported by case studies. The research demonstrates that implementing smoothness control during construction is essential to ensure post-completion track smoothness of super-long span bridges. The proposed strategy effectively translates smoothness control objectives into key construction phases. The virtual chord measurement method proves highly operable and effective for segmental assembly smoothness control. Post-completion multidimensional evaluations using chord measurement and other techniques can guide track smoothness adjustments. Conducting construction-phase smoothness control for super-long span bridges lays the foundation for achieving high track smoothness objectives on high-speed railway bridges.