<p>The key to the construction progress of petroleum refining engineering project groups lies in the production sub network, and the progress management of key projects is the core of sub network project progress management. This article proposes to use a design structure matrix to express the task relationships in key projects, comprehensively adjust the sequence progress of E+P+C, and achieve the goal of overlapping execution between processes by analyzing the start time, end time, and execution time of various work tasks, in order to shorten the project cycle and develop a reasonable schedule for key projects. This study can provide guidance for the preparation of EPC key project schedule plans in petroleum refining engineering project groups, and provide a scientific and effective basis for conducting research on project group schedule optimization management.</p>

错误:搜索内容不能为空,请输入英文关键词
错误:关键词超出字数限制,请精简
高级检索

Based on the Design Structure Matrix Optimization of EPC Project Schedule for Petroleum Refining Engineering

  • Lili Hu,
  • Sha He,
  • Lin Zhang,
  • Lingxiao Chen

摘要

The key to the construction progress of petroleum refining engineering project groups lies in the production sub network, and the progress management of key projects is the core of sub network project progress management. This article proposes to use a design structure matrix to express the task relationships in key projects, comprehensively adjust the sequence progress of E+P+C, and achieve the goal of overlapping execution between processes by analyzing the start time, end time, and execution time of various work tasks, in order to shorten the project cycle and develop a reasonable schedule for key projects. This study can provide guidance for the preparation of EPC key project schedule plans in petroleum refining engineering project groups, and provide a scientific and effective basis for conducting research on project group schedule optimization management.